ISB
Work in Progress
-
Continue pre cast and brick work along G line, lines 8 to 17.
-
Continue curtain wall installation at the east side of the building.
-
Continue monitor framing and glass at the north side of the building.
-
Continue last back filling in the east section of the building.
-
Last hydraulic slab pouring in the east side of the building is in progress.
-
Start slab on grade pouring on the north side, and 2” topping, from lines 1 to 7.
-
Start slab on grade pouring from lines 13 to 17, and 2” topping from lines 7 to 17.
-
Start framing for penthouse panels.
-
Start metal enclosure for stairs #3.
-
Start metal framing along north canopy and line A.
Looking Forward
-
Finalize pre cast and brick work along G line, from lines 8 to 17.
-
Continue metal framing work along north canopy and line A.
-
Continue MEP equipment installation in penthouse.
-
Continue slab on grade pouring at the east side of the building.
-
Continue back filling on the east side of the building.
-
Start metal enclosure for stairs #3.
Williams Hall
Work in Progress
-
Continue concrete final painting on the north side of the building.
-
Continue with CW work in tunnel.
-
Start installation of the mechanical curbs in basement.
-
Start installation of the switch gear in electric room.
Looking Forward
-
Finalize final painting concrete.
-
Continue with steam station work in mechanical room.
-
Continue with CW work in tunnel.
-
Continue with plumbing underground work.