Work in progress:
- Demolition of south stairs is complete including the foundations.
- Test pile will be tested on 1/29/16.
- Steam Condensate receiver in Williams Hall will take place on Saturday with UFM shutdown.
- Auger Cast pile installation to begin next week and progress south to column line 6 by end of week.
- Shoring is about 80% complete. Working on east side.
- Mass excavation continues on the South end.
Looking a week ahead:
- Tie in sanitary service lines extending south of the site inside fenced area.
- Pile caps and water proofing to start 2/8/16 .