2/18- Smith Hall Renovation Updates

Work in Progress:

  • CMU wall in the receiving and student machine shop is complete.
  • Working on electrical raceways on the second floor.
  • Completed demolition on the second floor.

Looking ahead:

  • Carpenters to start layout & framing on Monday in 101 & 104, 223 and machine shop.
  • Vent/beam patching from old uni-vents will start next week.
  • Pour slab on grade weather permitting next week.
  • Continue electrical rough-in on first and second floors.
  • Begin demolition of third floor lab  for restroom renovation.
POSTED: Thursday, February 18, 2016 12:40 PM