小黄片视频

3/17- Smith Hall Renovation Updates

Work in Progress:

  • New restroom plumbing rough-in nearly complete.
  • Sheet metal duct rough-in has begun on the first floor and the new restroom areas.
  • Electrical floor boxes are 75% complete in 223.
  • Sanitary drain and toilet carriers are complete in the second floor.
  • 3rd floor abatement for the restrooms is complete.
  • Poured the new addition floor slab was poured on 3/15/2016.

Looking ahead:

  • Continue with sheet metal duct installation on the first floor.
  • Pending electrical shutdown on 3/19/2016.
  • Water line installation will begin throughout the building to new restrooms.
  • Wall patching and drywall laminating will continue throughout the building.
  • Anchor bolt survey was completed on 3/16/2016 and steel is scheduled to be delivered the week of April 11th.
POSTED: Thursday, March 17, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM