Work in Progress:
- Pulling wire throughout for branch circuits.
- Installing duct on 1st floor.
- Complete domestic water rough-in on the 2nd floor.
- Sanitary piping rough-in has been completed on the 3rd floor.
- Completing remaining framing throughout.
- Starting door frame installation.
- Drywall delivery scheduled for 4/8/2016.
- Steel delivery was 4/6/2016 and columns have been erected.
Looking forward:
- Continue with steel erection.
- HVAC unit curb delivery will follow steel erection.
- Continue with HVAC duct on first floor.
- Drywall hanging and taping to begin.
- Door frame installation throughout.
- Continue with electrical wire pulling.